Canada: EPS-AB successfully introduces Ecomax® CHP technology into the Canadian Market
MFC Processing Partnership in Alberta awarded a contract for a 16.5 MW power plant. This will be the North-American introduction of the Ecomax SX, a modular CHP plant concept developed by Gruppo AB. This project utilizes 5 x Jenbacher J620 and is planned for start up in Spring 2015.
Polycon, a Magna company in Guelph, Ontario, awarded a contract for 3 x Ecomax 27 HE, Containerized CHP units with steam heat recovery. Total power output is 8 MW with 3 x Jenbacher J616. Start up is planned for Spring 2015.