Netherlands: Glazing started at Royal Peppers

The entire lower part of Royal Peppers has been constructed in no time at all. In less than five weeks all trellies, gutters and columns have been placed, and the gables have been finished. The ridge has been put into its final position everywhere. The underground rain water discharge has been installed and is hidden from view. This is the time for the glazing crews to suddenly appear, itching to get started. Last Friday it was time to start. Ever since construction started, progress has been closely monitored from above and from ground level, with photographs and movies as a result. Almost every week the drone took a look in Waddinxveen to keep track of it all.

Week 27


This is where you will enter the greenhouse

A week after the first steel was erected, almost three quarters of the construction was already installed. At the entrance of the greenhouse the last rain water discharge tubes are being dug in.


The mist had barely cleared in this picture. The speed at which this project is being built is only properly comprehended when viewed from above.


From above: Three quarters of the steel structure has already been constructed in just one week

Week 28
The inner structure of the greenhouse is finished, and work has shifted to the four gables. Digging works for the basins are almost completed.


The first purlins at the side gable have been bolted into position. This is the back side of the greenhouse, at the east, where the center aisle will be.


From above: the inner construction is finished, construction has shifted to the gables

Week 29


The head gables are nearly done, and the ridges have been installed

The gables are being finished. The head gables have been finished, leaving only the side gables.


From above: The head gables are almost finished. The ridges are in position.

Week 31


Glazing crews hard at work

Six glazing crews are working simultaneously to make sure the roof is closed in two weeks. After the roof is finished, the gables will be equipped with glass.


From above: Glazing has begun

For more information:
Havecon Kassenbouw
Marconistraat 32
2665 JE  Bleiswijk
Postbus 25
2665 ZG Bleiswijk
Netherlands
Tel. +31(0)10 266 32 70
Fax +31(0)10 266 32 71
info@havecon.com
www.havecon.com

Publication date: 8/9/2017

 


 

Other news in this sector:

6/22/2018 US (MO): Springfield wants to build greenhouse near landfill
6/22/2018 Mexico: Smart greenhouses to grow tomatoes
6/22/2018 US (MO): Aquaponics facility to alleviate food desert
6/21/2018 Antarctica: Plenty of production in Future Exploration Greenhouse
6/20/2018 Bolivia: Walipinis, underground greenhouses
6/20/2018 US: Ceres builds "most energy-efficient cannabis greenhouse in Colorado"
6/20/2018 Greenhouse vegetable growers await an average year after a gloomy start
6/20/2018 US (LA): Greenhouse renovations bring farm-to-table movement to campus
6/20/2018 Sweden: Greenhouse growers cover 286 hectares
6/20/2018 Russia: Mega greenhouse to arise in Tambov region
6/19/2018 Turkish greenhouses to provide food to 300,000 Mexicans
6/19/2018 Kenya: Courgette greenhouse pays off for student farmer
6/19/2018 Russia: New greenhouse to be built in Tambov region
6/19/2018 Podcast offers insider tips for greenhouse pros
6/19/2018 CAN (ON): Jan VanderHout addresses new Premier Designate
6/19/2018 CAN (ON): Hamilton looking to increase allowed size of MJ greenhouses
6/19/2018 US (CA): Smart Cannabis retrofits greenhouses in Monterey County
6/18/2018 "Russia needs another 1,800 hectares of vegetable greenhouses"
6/18/2018 Thai melon grower makes €2,600 per 60 m2 greenhouse
6/18/2018 Atlas Obscura visits tomato greenhouse in Iceland