Netherlands: Glazing started at Royal Peppers
Week 27
This is where you will enter the greenhouse
A week after the first steel was erected, almost three quarters of the construction was already installed. At the entrance of the greenhouse the last rain water discharge tubes are being dug in.
The mist had barely cleared in this picture. The speed at which this project is being built is only properly comprehended when viewed from above.
From above: Three quarters of the steel structure has already been constructed in just one week
Week 28
The inner structure of the greenhouse is finished, and work has shifted to the four gables. Digging works for the basins are almost completed.
The first purlins at the side gable have been bolted into position. This is the back side of the greenhouse, at the east, where the center aisle will be.
From above: the inner construction is finished, construction has shifted to the gables
Week 29
The head gables are nearly done, and the ridges have been installed
The gables are being finished. The head gables have been finished, leaving only the side gables.
From above: The head gables are almost finished. The ridges are in position.
Week 31
Glazing crews hard at work
Six glazing crews are working simultaneously to make sure the roof is closed in two weeks. After the roof is finished, the gables will be equipped with glass.
From above: Glazing has begun
For more information:
Havecon Kassenbouw
Marconistraat 32
2665 JE Bleiswijk
Postbus 25
2665 ZG Bleiswijk
Netherlands
Tel. +31(0)10 266 32 70
Fax +31(0)10 266 32 71
info@havecon.com
www.havecon.com